Back to News

California Energy Code · Title 24, Part 6

Title 24 occupied-standby in the 2025 Energy Code

Effective · Published

A short summary of what California's 2025 Building Energy Efficiency Standards require for occupied-standby controls, with links to the official documents.

This page is a summary for building owners, facilities teams, and integrators. It is not legal advice and is not a substitute for the Energy Code or the Nonresidential Compliance Manual. The official standards and the local enforcing agency control what a project must do. KenergyAI does not certify compliance.

What the 2025 standards are

The Building Energy Efficiency Standards (the Energy Code) are in the California Code of Regulations, Title 24, Part 6. The California Energy Commission (CEC) adopts them and updates them every three years. They set energy and ventilation requirements for newly constructed buildings, additions to existing buildings, and alterations to existing buildings.

Sources: CEC Building Energy Efficiency Standards; 2025 Energy Code publication page (CEC-400-2025-010).

When they apply

The 2025 Building Energy Efficiency Standards took effect January 1, 2026. Buildings whose permit applications are applied for on or after January 1, 2026, must comply with the 2025 Energy Code.

Sources: CEC Building Energy Efficiency Standards (“will go into effect January 1, 2026”); CEC 2025 Building Energy Efficiency Standards page (“Buildings whose permit applications are applied for on or after January 1, 2026, must comply with the 2025 Energy Code.”).

What occupied-standby requires

Occupied-standby is a mandatory HVAC control sequence in Title 24, Part 6. It applies when a zone is scheduled to be occupied, but occupant sensors show that the spaces served by the zone are vacant. It does not turn all conditioning off for good. In occupied-standby mode, mechanical ventilation to the zone is shut off, and heating and cooling setpoints are reset (cooling is set up and heating is set back). Ventilation can still run if it is needed to heat or condition the space.

The Energy Code splits the timing into two steps:

  • In 20 minutes or less after no occupancy is detected, occupant sensing controls must indicate that the room is vacant. If one zone serves more than one space, each space needs a sensor, and the zone is not vacant until all of those spaces are vacant. (Section 120.1(d)5B.i and iii)
  • When the zone is scheduled to be occupied and all spaces it serves are unoccupied, the zone is placed in occupied-standby mode. (Section 120.1(d)5B.v)
  • In 5 minutes or less after entering occupied-standby mode, mechanical ventilation to the zone is shut off until the space becomes occupied or ventilation is needed for space heating or conditioning. The ventilation system must also reduce the system outside air rate by the amount required for that zone. (Section 120.1(d)5B.vi)
  • In the same 5-minute window, where the system that conditions the space also provides the ventilation, zone setpoints must be reset: raise the cooling setpoint by 2°F or more and lower the heating setpoint by 2°F or more; or, for multiple-zone systems with direct digital controls (DDC) to the zone level, raise cooling and lower heating by 0.5°F or more. Mechanical ventilation is to remain off while the space temperature is between the active heating and cooling setpoints. (Section 120.2(e)3)

The 2025 Nonresidential Compliance Manual describes this as a total delay of up to 25 minutes (a sensor delay of up to 20 minutes, plus up to 5 minutes after the zone enters occupied-standby mode) before ventilation to the rooms is shut off.

One hour before normal scheduled occupancy, the controls must still allow the pre-occupancy purge required by Section 120.1(d)2. Occupied-standby does not cancel that purge.

Lighting occupant sensors may be used for ventilation if the ventilation signal is independent of daylighting and of manual lighting overrides or manual lighting control. (Section 120.1(d)5B.ii)

Sources: 2025 Building Energy Efficiency Standards, Sections 120.1(d)5 and 120.2(e)3, in CEC-400-2025-010-F (PDF); 2025 Nonresidential Compliance Manual, Occupied Standby Zone Controls, in CEC-400-2025-008 (PDF).

Which spaces

Section 120.1(d)5A requires occupied-standby controls on a space-conditioning zone when all of the following are true:

  • All rooms served by the zone are permitted to have their ventilation air reduced to zero in occupied-standby mode, per Table 120.1-A; and
  • Occupant sensors are required by Section 130.1(c)5 and 6; and
  • The zone and ventilation system are not served by pneumatic controls.

Table 120.1-A, Note F, says ventilation air for listed occupancy categories “shall be permitted to be reduced to zero when the space is in occupied-standby mode.” Examples of occupancies that carry Note F include office space, conference and meeting rooms, corridors, reception areas, lecture and postsecondary classrooms, and multiuse assembly. The table also includes other Note F occupancies, such as certain lobbies and public assembly spaces. The official table, not a shortened list, is what controls.

Not every classroom qualifies. In Table 120.1-A, “Classrooms (ages 5-8)” and “Classrooms (age 9-18)” do not have Note F, while “Lecture/postsecondary classroom” and “Lecture hall (fixed seats)” do. A zone must also have occupant sensing (not only a time switch) under Section 130.1(c)5 or 6. If a zone serves a mix of spaces, all rooms served by that zone have to meet the ventilation-to-zero permission before the occupied-standby mandate in Section 120.1(d)5A applies.

Section 120.2(e) includes exceptions, including systems that must operate continuously (when demonstrated to the enforcing agency) and some small systems with a manual shut-off. Healthcare facilities are excepted from Section 120.2(e). Hotel and motel guest rooms also have a separate setpoint-reset requirement in Section 120.2(e)4, with a 30-minute vacancy delay and a 5°F setup or setback. That guest-room rule is not the same as the 20-minute plus 5-minute occupied-standby sequence above.

Sources: 2025 Building Energy Efficiency Standards, Sections 120.1(d)5A, Table 120.1-A (including Note F), 120.2(e)3 and 120.2(e)4, and Section 130.1(c), in CEC-400-2025-010-F (PDF). The 2025 Nonresidential Compliance Manual and Energy Code Ace's occupied-standby table also discuss qualifying occupancy categories, with the Energy Code Ace page citing the CEC as its source.

Existing buildings, additions, and alterations

The Energy Code is not only a new-construction code. The CEC states that it contains requirements for newly constructed buildings, additions to existing buildings, and alterations to existing buildings. The 2025 Nonresidential Compliance Manual includes an “Additions and Alterations” discussion in Chapter 4 (Mechanical Systems).

That does not mean every existing campus or office building must add occupied-standby controls on January 1, 2026. Whether a specific existing-building project must include these controls depends on the project scope and on the Energy Code rules for additions and alterations. Confirm the applicable sections with the official Energy Code, the Nonresidential Compliance Manual, and the local enforcing agency that issues the permit.

Buildings permitted under earlier code cycles are not automatically required to be brought up to the 2025 occupied-standby rules unless a later project triggers those requirements.

Sources: 2025 Energy Code publication page; 2025 Nonresidential Compliance Manual, Chapter 4, Additions and Alterations, in CEC-400-2025-008 (PDF).

Official sources

Start with these California Energy Commission documents and pages. The Energy Code is the regulation. The compliance manual and Energy Code Ace materials are guidance.

How this relates to KenergyAI

KenergyAI provides AI Occupancy Based HVAC Controls software. In buildings that already have occupancy sensors or networked lighting controls, plus a BACnet building management system, the software can apply the same occupied-standby idea: run occupied comfort when people are there, and ease off empty zones, without a capital project or a change to BMS sequences.

KenergyAI does not certify compliance with Title 24, Part 6, or with any other code or program. Building owners, design teams, and the local enforcing agency are responsible for determining what a project must do and for demonstrating compliance. If you have a question about a specific building, start with the official sources above.

To talk with KenergyAI about a campus or office portfolio, visit kenergyai.com.

Back to News

Cookie settings

Choose which cookies you allow. You can change these settings at any time from the "Cookie settings" link in the footer. Learn more in our Cookie Policy and Privacy Policy.

Strictly necessary Always on

These cookies are required for the site to work and stay secure, such as remembering your cookie choices and protecting our contact form from spam. They can't be turned off here.

Analytics Off by default

These cookies help us understand how visitors use our site, such as which pages are most useful, so we can improve it.